48 radial gates of Polavaram spillway installed- The New Indian Express

2022-10-15 00:58:21 By : Ms. Rose Wong

Out of 96 hydraulic cylinders, 84 have been fixed and 12 for six gates to be installed soon to operate radial gates

Published: 14th March 2022 06:39 AM   |   Last Updated: 14th March 2022 06:39 AM   |   A+ A  A-

The Polavaram project spillway after installation of radial gates I Express

VIJAYAWADA: Reaching another milestone, Megha Engineering and Infrastructures Ltd (MEIL) has completed installation of 48 radial gates of the spillway of the Polavaram Irrigation Project. Installation of radial gates commenced on December 17, 2020 and 42 radial gates were installed before the onset of flood season last year.  The flood water was diverted through the spillway and the installed gates had helped in regulating the flow. Now, the remaining six gates were also installed.  

Out of the 96 hydraulic cylinders that have to be fitted to the radial gates, 84 have been fixed and 12 cylinders for the six gates will be installed shortly and once it is completed the gates can be operated.

Further, all 24 power pack sets required for operating the gates have already been installed. Similarly, the 10 river sluice gates and 20 hydraulic cylinders with 10 power packs to operate the gates were also installed. 

The important works of fish ladder pertaining to the spillway have also been completed and the guide bund on the left side of the spillway is expected be completed soon. 

According to PIP officials and MEIL engineers, 97.25% of the spillway concrete works have been completed. A total of 3,32,114 cubic metres of concrete works have been done. 

Water Resources Department Superintending Engineer Srinivas Yadav, Executive Engineers Sudhakar and Adi Reddy, MEIL CGM Muddu Krishna, DGM Rajesh Kumar, manager Murali and others visited the spillway to witness the completion of radial gates installation of the project.

The State government is determined to complete the Polavaram project by 2023. As announced by Finance Minister Buggana Rajendranath Reddy in the State Assembly during the budget presentation on March 11 in this regard, the project construction works have been put on fast-track. Recently, the Ministry of Environment, Forest and Climate Change (MoEFCC) issued a memorandum keeping the ‘Stop Work Order’ of the Polavaram project in abeyance till July 2, 2023.

During his meeting with Prime Minister Narendra Modi in January, Chief Minister YS Jagan Mohan Reddy urged the Centre to approve the Rs 55,657 crore Revised Cost Estimates of the Polavaram project at 2017-18 price level at the earliest. The acquisition of land and rehabilitation and resettlement (R&R) of project oustees account for a major portion of project expenditure, he said. 

It was followed by YSRC MPs meeting Jal Shakti Minister Gajendra Singh Shekhawat seeking early completion of the project. During his visit to Polavaram project, along with the Chief Minister on March 4, Shekhawat had promised to ensure completion of the project at the earliest and even agreed to review its progress every fortnight. 

As per the data of the socio-economic survey released by the State government during the ongoing budget session of Assembly, 42.56% of the Polavaram project, including, land acquisition and R&R till elevated levels of +45.72 metres has been completed as of December 2021. It includes 75.75% of headworks, 92.57% of the right main canal and 71.24% of the left main canal. If only various components of the project is taken into consideration, the completion rate is 77.91%.

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.

HC acquits ex-DU prof Saibaba in Maoist links case, calls his sanction under UAPA 'bad in law'

Father of Chennai girl killed by stalker dies after allegedly consuming poison

Gyanvapi case: Varanasi court rejects plea seeking carbon dating of 'shivling'

UK PM Liz Truss sacks Kwasi Kwarteng as Chancellor amid economic turmoil

2017 convention followed in not announcing Himachal, Gujarat polls together: CEC

90 per cent of leadership positions in Indian media occupied by upper caste groups: Report

The Morning Standard | Dinamani | Kannada Prabha | Samakalika Malayalam | Indulgexpress | Edex Live | Cinema Express | Event Xpress

Contact Us | About Us | Careers | Privacy Policy | Search | Terms of Use | Advertise With Us

Home | Nation | World | Cities | Business | Columns | Entertainment | Sport | Magazine | The Sunday Standard